Wallstein Holding GmbH & Co. KG

_New orders

T.A. Lauta Laogang TRV Wesseling AlexFert Company, Egypt


T.A. Lauta

Project description:               Engineering, construction and fabrication of SCR steam-gas preheater for two lines to increase the flue gas temperature. Executed as a fin-tube insertion-mounted assembly. Including removal of the existing register, installation of the new heat exchanger and connection to the pipe system.

Client:                                 Vattenfall Europe AG

 

Technical data:                     Flue gas rate 97145 kg/h

                                          Heating from 144 degrees C to 184 degrees C

Receipt of order:                   11/2011

Status:                                Detail engineering

 

TRV Wesseling

Project description:               Construction and fabrication of a flue gas preheater. Implemented as a rectangular u-pipe insertion bundle with welded water chambers.

Client:                                 Thermische Rückstandsverwertung GmbH & Co. KG

Technical data:                     Allowable positive operating pressure 32 bar

                                          Design temperature 270 degrees C

Receipt of order:                   12/2011

Status:                                Detail engineering

 

Laogang

Project description:               Engineering, construction, fabrication and installation of a two-stage and leak-free gas-gas heat exchanger for reheating the clean gas with the flue gas. Implemented as a straight-tube cross-flow heat exchanger, consisting of fluoroplastic tubes and a foil-lined carbon steel casing.

Client:                                 Nanjing Longyuan Environmental Co., Ltd.

Technical data:                     gas-gas heat exchanger 150,770 Nm³/h

                                          Q=3660kW

                                          Cooling flue gas from 170°C to 108°C

Receipt of order:                    06/2011

Status:                                Detail engineering

 

AlexFert Company, Egypt

 

Project description:               As part of a revamp, the capacity of the ammonium sulphate plant supplied by Uhde Dortmund will be increased. To these ends, WIG received an order for engineering, construction and fabrication of a steam-air preheater with extruded aluminium fins.

Client:                                 Uhde, Dortmund

Technical data:                     Airflow rate 50000 kg/h

                                          Heat from 32 degrees C to 45 degrees C,

                                          Thermal output        210 KW

Receipt of order:                    12/2011

Status:                                Detail engineering