Wallstein Holding GmbH & Co. KG

_New orders

Engineering, construction and fabrication


Bandirma Gübre Fabrikalan A.S. (BAGFAS)
Project description:ThyssenKrupp Uhde from Dortmund is supplying the Turkish company BAGFAS with a plant for the manufacture of calcium ammonium nitrate fertiliser.
As part of this, WIG was awarded the contract for the engineering, design, construction and delivery of a NH³ evaporator for air dehumidification with downstream droplet separator and subsequent re-heating by means of a steam air pre-heater (Air Conditioning Unit).
Client:ThyssenKrupp Uhde, Dortmund
Technical data:

Air Conditioning Unit

Airflow rate 250000 kg/h
Cooling from 29 °C to 7 °C,
Fluid loss about 3100 kg/h
Cooling capacity 36800 KW
Heating from 7°C to 15°C
Thermal capacity 680 KW

Receipt of order:04/2013
Status: Detail engineering
Bandirma Gübre Fabrikalan A.S. (BAGFAS)
Project description:ThyssenKrupp Uhde from Dortmund is supplying the Turkish company BAGFAS with a plant for the manufacture of calcium ammonium nitrate fertiliser.
In this regard, WIG received a further order for engineering, construction, manufacturing and supply of steam-heated air pre-heaters:
Drying Air Heater, Injection Air Heater and Air Heater.
Technical data:

Drying Air Heater

Airflow rate 250000 kg/h
Heat from 55 °C to 80 °C,
Thermal capacity 1760 KW

Technical data:Injection Air Heater

Airflow rate 15276 kg/h
Heat from 29 °C to 85 °C,
Thermal capacity 235 KW
Technical data:Air Heater

Luftmenge 265000 kg/h
Aufheizung -8 Grad C auf 10 Grad C,
Wärmeleistung 1350 KW
Receipt of order:05/2013
Status: Detail engineering
Tongmei Datang Tashan Power Generation Co., Ltd
Project description:Engineering, design and manufacturing of flue gas coolers for two lines to recover heat for boiler feed water pre-heating
The scope of supply includes 2x 6 pieces flue gas coolers  including the system technology consisting of the engineering and supply of interconnecting piping, valves, pumps, the necessary structural steel and electrical and I&C engineering, as well as supervising installation and commissioning
Client:Tongmei Datang Tashan Power Generation Co., Ltd.
Technical data:Flue gas volume 3,446,368 kg/h
Cooling from approx. 130 °C to 90 °C
Extracted heat approx. 42 MW
Receipt of order:06/2013
Status:Basic engineering